The state government plans to replace multiple valves in the new Perth Children's Hospital after a report confirmed the cause of ongoing lead contamination at the trouble-plagued project, wth the extra work to push the hospital's opening date beyond this year.
The Western Australian Building Commission is expanding its audit of aluminium composite panels following the Grenfell Tower fire in London last month.
Western Australia's biggest builders are facing higher insurance costs, in some cases understood to be as high as 25 per cent more, as the Building Commission moves to reduce the reliance on taxpayers to foot the bill for failures in the sector.
UPDATED: Building commissioner Peter Gow has issued a clarifying statement today (Tuesday), essentially confirming the state government's view that lead leaching directly from brass fittings remains the only significant source of lead at Perth Children's Hospital.
One of state's biggest residential construction firms, Builton Group, has succumbed to the financial stresses engulfing the sector, appointing an external administrator earlier today after reports of the company's financial troubles emerged last week.
The Building Commission's Building Services Board has imposed conditions on two Diploma Group subsidiaries, limiting their ability to carry out work, after the parent company fell into the hands of administrators just before Christmas.
An Osborne Park-based building company and its nominated supervisor have been fined a combined $45,000 for negligent work that led to the roof of one house blowing off and another being badly damaged during a storm.
A now de-registered Perth-based builder has been fined $15,000 and ordered to pay $3,200 in costs after he was found to have engaged in deceptive conduct.
The supervisor of Dianella-based building company Frayson has been fined $15,000 for failing in his duties as a manager and supervisor on work carried out at 20 Perth properties over a 10-year period.
The builder of the $1.2 billion Perth Children's Hospital has not been blamed for asbestos found in ceiling panels but should have done more to protect the health of workers, an inquiry has found.
Osborne Park-based builder Quattro Homes has been placed into administration, the fourth residential builder in Western Australia to collapse in the past three months.
Slowing residential construction has claimed more scalps, with the flow-on effects likely to have negative repercussions for the affordability of new housing.
The state's building commissioner says contractors and suppliers need to be paid within 50 days, as controversy over the extension of Rio Tinto's payment terms continues.
Yangebup building company Bellagio Homes has been formally cautioned by the Building Commission's building services board for falling to comply with State Administrative Tribunal orders.
Building Commission head Peter Gow has called for more checks and balances in Western Australia's housing construction sector to ensure there is no repeat of the collapse of Capital Works Constructions.
Builders have been invited to bid for the upcoming and current work of collapsed home builder Capital Works Constructions, in the wake of the company calling in administrators last week.