West Perth-based Equinox Minerals has accepted handover of the process plant and related infrastructure at its Lumwana copper project in Zambia.
West Perth-based Equinox Minerals has accepted handover of the process plant and related infrastructure at its Lumwana copper project in Zambia.
The project was secured through a $103 million loan facility, underwritten by a banking syndicate.
Initial concentrate is expected to be produced next week, with shippable quantities of commercial grade concentrate from December 2008.
Original estimates for total pre-production capital expenditure was budgeted at $758 million, howvere this has since been re-estimated to be $814 million the extensive fire caused by and incident with a transformer which delayed the project for 4 months.
Although, the actual costs to complete the project, had the fire incident not occurred, were in line with the original budget.
Equinox president and chief executive, Craig Williams was pleased to commence ore commissioning and production ramp up.
"We are very pleased to bring on line the largest copper mine on the African continent which will not only be a long term, low cost copper producer, but will make a major economic and social contribution to Zambia," he said in a statement.
Full announcement below:
Handover of Lumwana Processing Facilities Accepted by Equinox
NOT FOR DISTRIBUTION TO U.S. NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE U.S.
Equinox Minerals Limited (TSX and ASX symbol: "EQN") ("Equinox" or the "Company") is pleased to
announce it has accepted from its EPC Contractor (a joint venture between Ausenco Projects Limited and
Bateman International Projects BV) handover of the process plant and other related infrastructure at its
Lumwana Copper Project ("Project"), reaching Practical Completion and attaining the final milestone under
the EPC contract.
Equinox reported on October 7, 2008 that crushing of material at the primary crusher had commenced with
the 4.5km conveying circuit transporting crushed material to the fine ore stockpile at the copper concentrator.
Plant commissioning with ore will now commence and plant ramp up will take place over the coming months.
Initial concentrate is expected to be produced next week, with shippable quantities of commercial grade
concentrate from December 2008.
Total pre-production capital expenditure is expected to be $814 million, compared to the budget of $758
million estimated prior to the transformer incident which delayed the project for 4 months. This includes all
mining fleet costs, clearing and pre-stripping costs, the EPC Contractor's cost to complete the 20Mtpa
process plant, tails and water facilities and owners costs as well as operating consumables and additional
mining activity, fixed costs necessarily incurred as a result of the delay and liquidated damages proceeds
received from the EPC Contractor of $27 million. In addition, the delay in start-up insurance proceeds are
currently being processed. The actual costs to complete the Project, had the fire incident not occurred, were
in line with the original budget.
As reported in the results for the Quarter ended September 30, 2008, Equinox had cash resources of
US$51.8 million and undrawn debt facilities of US$151.4 million plus a $45 million cost overrun facility. The
outstanding capital commitments of the Company relating to the construction of the Lumwana Mine (which
are incorporated in the expected total cost of $814 million) at September 30, 2008 were $55.1 million.
Mr Craig Williams, Equinox's President and CEO commented, "Equinox is pleased to accept handover of the
Lumwana process facilities and commence ore commissioning and production ramp up. We are very
pleased to bring on line the largest copper mine on the African continent which will not only be a long term,
low cost copper producer, but will make a major economic and social contribution to Zambia. I would
personally like to thank our EPC Contractors Ausenco-Bateman, and pay particular tribute to Equinox
management and employees whose outstanding efforts, project management skills and resolve have
delivered a high quality asset at a remarkably low capital cost."