Cosmos project cost hits $825m

IGO has substantially increased the scope and cost of its Cosmos nickel project while also reporting commissioning delays at the Kwinana lithium refinery.
The cost of the Cosmos project has increased to between $795 million and $825 million.
This was up from a $425 million cost estimate implied by the independent expert report published by KPMG in April, as part of IGO’s takeover of Western Areas.
IGO attributed the cost increase to three factors.
The nameplate capacity for the Cosmos process plant has been increased from 750,000 tonnes per annum to 1.1mtpa.
This change, and other measures to optimise the project, such as accelerated underground mine development, added $150 million to the expected cost.
IGO has added a further $140 million for items that were previously classified as sustaining capital or operating costs.
A further $95 million relates to “clear omissions, rectifications, refurbishments and escalations that were not included in the IER, that IGO has deemed necessary in order to deliver a safe, efficient and reliable operation.”
IGO said $302 million had already been spent on the project as at June 30 2022.
Most of the remaining cost is budgeted to be spent in the current financial year, with the process plant due to be completed in the first of FY24 (September 2023).
The miner plans to commence production from ore stockpiles at this time, ahead of completion of the shaft and other underground infrastructure.
GR Engineering Services said the increased scale of the process plant meant the value of its EPC contract had increased from $48 million to $76 million.
IGO’s quarterly report also provided an updated on the Kwinana lithium refinery, jointly owned by Tianqi Lithium (51 per cent) and IGO (49 per cent).
After achieving the first production of battery-grade lithium hydroxide earlier this year, IGO said work was continuing on rectification and debottlenecking of the facility.
The expected date for declaring commercial production for train one has been pushed out to the end of CY23.
When IGO bought into Tianqi in 2020, it said train one was due to complete ramp up in Q4 2022.
It added that $13.1 million was spent during the September quarter on train two ahead of a final investment decision (FID) on the resumption of construction.
It had been targeting FID in the second half of CY22, but has given itself more flexibility by saying FID would occur at some time during FY23.
Its work on train two has included engineering and design, development of construction tender packages and negotiating an EPCM contract with Lycopodium.
The latest cost estimate for the completion of train two is $328 million.
Meanwhile, IGO has reported a strong lift in earnings, boosted by its wholly owned nickel mines and its minority stake in the Greenbushes lithium mine.
It had record sales revenue from nickel while Greenbushes achieved record production.
The company reported a 54 per cent lift in quarterly EBITDA to $398 million.
IGO’s share price slipped 1.5 per cent to $15.29 today.