Federal Court sets aside minister’s $1.1b Regis block

The Federal Court has set aside a 2024 ministerial decision to block the construction of a tailings dam at Regis Resources’ billion-dollar McPhillamys gold project in NSW.
The decision comes following years of legal wrangling over the decision by former environment minister Tanya Plibersek and paves the way for the project’s construction after two years of malaise.
Regis had fully permitted the project near Blayney and was nearing a final investment decision in 2024, when the minister used confidential cultural heritage grounds to block the location of a critical tailings facility.
The call was made based on in-confidence evidence provided by local elders about a Dreamtime story relating to the blue-banded bee, and sparked debate over competing claims for cultural authority in the jurisdiction.
Regis had consulted with the Orange Local Aboriginal Land Council on the McPhillamys, which supported the project, but the appeal came from a different Native Title group.
At the time Regis wrote the value of the project down to zero and immediately lodged a legal appeal, with suggestions that McPhillamys may have been dead in the water.
While pursuing its legal avenues, Regis went back to the drawing board and devised a new plan for tailings processing at the site.
Its managing director Jim Beyer told Business News in July this year that while the project now had multiple pathways to development, the original tailings site was the preferred way forward.
The court found the decision was invalid due to a “material deficiency in the process of making the declaration”.
It said the minister’s declaration was made without authority because the blue-banded bee story should have constituted a new application against the mine.
Regis issued a statement welcoming the Federal Court’s decision, and said the path forward would be for a redetermination by new Environment Minister Murray Watt.
It remains hopeful of a redetermination but said alternative development approaches were on the cards if the next outcome was not in its favour.
“The judgement finding that the Section 10 declaration is legally invalid vindicates the position we have held since the declaration was made in August 2024, and we are extremely pleased the court has agreed,” Mr Beyer said.
“After considerable delay and uncertainty, and more than two years of time lost, we are eager to move forward.
“We look forward to engaging constructively with the department through the redetermination process, and to advance one of Australia’s largest undeveloped gold projects – one with the potential to deliver lasting economic and social benefits to the central New South Wales region and our broader stakeholder community.”
The Minerals Council of Australia lauded the Federal Court’s call.
MCA chief executive Tania Constable said the decision would help restore confidence in Australia’s regulatory processes.
“Australian mining investment relies on certainty of process, even if the outcomes of that process are not certain,” she said.
“Support for responsible mining and protecting Aboriginal cultural heritage are not competing or mutually exclusive objectives.
“Both depend on transparent decision-making, credible evidence and meaningful recognition of the appropriate Traditional Owner representatives.”
Regis expects McPhillamys to take two years to build.
The Association of Mining and Exploration Companies - of which Mr Beyer is president - said the outcome was common sense, and that there should be no further delay to development.
“The Federal Environment Minister, Murray Watt, should waste no further time in reconsidering this matter and clearing the way for the project to proceed.
“McPhillamy’s has already faced years of uncertainty, and further unnecessary delays would only compound the damage to investment confidence and the regional economy,” chief executive Warren Pearce said.
“Australia cannot afford an approvals system where major projects can be derailed after years of assessment, consultation and investment.
“We must protect cultural heritage, but we must also have a system that is fair, transparent, consistent and gives investors confidence that the rules will be applied correctly.”
The project has an ore reserve of 56 million tonnes at 1.1 grams per tonne gold, for 1.89 million ounces of gold.
It is likely to cost $1.1 billion to build. It would be Regis' only producing asset outside of Western Australia.