Empire hit by second cost blow-out
You have no credits left. To view this article subscribe to Business News.
You have used {{points}} and have {{current_points}} remaining. Your credits will reset on {{reset_date}}.
This article is part of a special report and is available to paid Business News subscribers only.
You can purchase access to this special report or subscribe to Business News.
You can purchase access to this special report or subscribe to Business News.
This article is premium content and is available to paid Business News subscribers only.
Subscribe to Business News.
Subscribe to Business News.
Friday, 20 September, 2013 - 14:10
Category:
Empire Oil & Gas has revealed a 10.9 per cent blowout in the cost of building and commissioning its Red Gully gas plant near Gingin.
The company said today that the total cost of the facility was $38.7 million, up from its previous guidance of $34.9 million, released in April.
Before that, the company had estimated the project would cost $29.1 million.
First gas and condensate was produced at the plant in June.
It is currently producing 8 terajoules of natural gas each day, which is sold to alumina producer Alcoa, which invested $25 million in the project.
The plant also produces 500 barrels of condensate per day, which is trucked to the BP refinery in Kwinana.
At 2:00PM, WST, Empire stocks were steady at 1.3 cents.
Companies: